Lifting of the ship "Atlantic Navigator"
Lifting and pulling of the ship weighing 2800 tons - Rijeka, CroatiaPlankos d.o.o. has designed the system and realized the project of lifting and pulling of the bow of the ship "Atlantic Navigator".
Lifting and pulling of the ship's bow weighing 2800 tons has been made with Enerpac equipment on the floating dock in the shipyard "Viktor Lenac".
Lifting has been performed in ten points. Distance beetween cylinders was 7 meters and the center of mass was on 11 meter height. After the cutting of the ship, the bow was lifted and moved for 30 meter and the new section of the ship was inserted and welded.